BarBot/Project timeline

From Nottinghack Wiki
< BarBot
Revision as of 23:56, 3 April 2014 by Mousetad (talk | contribs) (Created page with " == BarBot Project Timeline == {| class="wikitable" |- ! ID ! Start Date ! End Date ! Description ! Dependencies |- | 1 || 2014-04-03 || 2014-06-19 || Build prototypes: disp...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

BarBot Project Timeline

ID Start Date End Date Description Dependencies
1 2014-04-03 2014-06-19 Build prototypes: dispensers -
2 2014-04-03 2014-06-19 Build prototypes: delivery -
3 2014-04-03 2014-07-31 Database, UI, recipe execution s/w (on RPi) -
4 2014-04-03 2014-06-19 Real-time (hardware control) software concurrent with: 1, 2
5 2014-06-19 2014-06-19 Decide which dispensers to use, overall machine design (how many of each dispenser and so on) 1, 2, 4
6 2014-06-19 2014-08-20 Build phase: multiple dispensers, frame, power infra. 5