BarBot Project Timeline
ID | Start Date | End Date | Description | Dependencies |
---|---|---|---|---|
1 | 2014-04-03 | 2014-06-19 | Build prototypes: dispensers | - |
2 | 2014-04-03 | 2014-06-19 | Build prototypes: delivery | - |
3 | 2014-04-03 | 2014-07-31 | Database, UI, recipe execution s/w (on RPi) | - |
4 | 2014-04-03 | 2014-06-19 | Real-time (hardware control) software | concurrent with: 1, 2 |
5 | 2014-06-19 | 2014-06-19 | Decide which dispensers to use, overall machine design (how many of each dispenser and so on) | 1, 2, 4 |
6 | 2014-06-19 | 2014-08-20 | Build phase: multiple dispensers, frame, power infra. | 5 |