Hackspace 2.5/ToDo: Difference between revisions

From Nottinghack Wiki
Jump to navigation Jump to search
Q4 2025 major revision
No edit summary
 
(5 intermediate revisions by the same user not shown)
Line 1: Line 1:
===Metalworking===
=Metalworking=


====Phase Zero: Lighting====
==Electrical==


Electrical:
* Hang lights (complete except grinding room + one in far corner)
* Hang lights (done, except grinding room + one in far corner)
* Install conduit
* Install conduit (done)
* Install trunking
* Install trunking (WIP)
* Pull cable
* Pull cable
* Install temporary control box / switching solution
* Install temporary control box / switching solution
* Install control box feed (10A RCBO from main board, PVC conduit)
* Install control box feed (10A RCBO from main board, PVC conduit)
* Test & Inspection
* Test & Inspection, issue EIC
* Remove last of temporary lighting solution
* Remove last of temporary lighting solution  
* 13A power circuit on near wall ✅
 
* 13A power circuit on dance studio wall ✅
Non-electrical:
* Finish ceiling in far corner to allow final light to be hung
 
====Phase One: Welding & Grinding====
 
Electrical:
* Welding interlock (WIP)
* Welding interlock (WIP)
* Heavy feed to interlock box (D63 - reuse from metalworking feed upstairs?)  
* Heavy feed to interlock box (D63 - reuse from metalworking feed upstairs?)  
* Install welding sockets - will require them being removed from upstairs (trunking/SWA)
* Install welding sockets - will require them being removed from upstairs
* 16/3 supply to grinding room, but see below
* Test & Inspection
* Install small power circuit to bay (galv conduit)
* Make and install unistrut post for bandsaw socket
* 16/3 Socket for bandsaw (SWA on tray from DB down post to RCD in small box, RCD to socket)
* Complete traywork install
* Make and install rest of unistrut posts
* Install back wall small power circuit
* Install posts small power circuit (routing???)
* Corridor power circuit (PVC conduit)
* Install power for compressor (seperate feed, or tacked on to the end of the corridor power circuit)
* Test & Inspection, issue EIC
* Test & Inspection, issue EIC


Non-electrical:
===Blocked Tasks===
* Move door from grinding room to far end of room
* All of small grinding room
* Hanging final light
 
==Non-Electrical==
* Put the rest of the diffusers on the lights
* Plug in the batteries on the emergency lights (technically electrical I suppose)
* Move door currently on grinding room to far end of room
* Establish what else needs to be done to the grinding room before it's sensible to install electrics in there (finish walls, boxing, etc)
* Establish what else needs to be done to the grinding room before it's sensible to install electrics in there (finish walls, boxing, etc)
* Move stuff out of the way (particularly the pallet of metal things and the Warco - eek.)  
* Move stuff out of the way (particularly the pallet of metal things and the Warco - eek.)  
* Install curtains/other dividing to ensure that grinding dust is kept out of the rest of the area
* Design and install curtains/other dividing solution between welding quarter and the rest of the room to ensure that grinding dust is mostly kept out of the rest of the area
* Consider the ventilation situation
* Design and install ventilation setup for welding
 
* Finish ceiling in far corner of main space to allow final light to be hung
====Phase Two: The rest====
* Data cabling for NH-Tools
 
* Move tools / benches etc into place!
Electrical:
* Handles for doors
* Complete the traywork
* Investigate possible leak in grinding room?
* Heavy feeds (3x 16/3)
* Small power circuits (galv conduit)
* Corridor power circuit (PVC conduit)
* Install power for compressor (seperate feed or tacked on to the end of the corridor power circuit)


Non-electrical:
* Install unistrut posts on the pillars ala Dusty Area
* Remove random leftover wood, insulation, etc
* Data cabling for NH-Tools
* Move tools / benches etc into place!


====Epilogue====
==Epilogue==
* Christen the room by smashing a bottle of Lucozade on it's bow (step one, find its bow...)  
* Christen the room by smashing a bottle of Lucozade on it's bow (step one, find its bow...)  
* Remove all infra tools/supplies from Downstairs Members' Storage to Team Storage
* Remove all infra tools/supplies from Downstairs Members' Storage to Team Storage
* Consider fire door (opening inwards probably not acceptable?)  
* Consider fire door (opening inwards probably not acceptable?)  
* Have Schneider DB disconnected and sell it on eBay  
* Have Schneider DB disconnected and sell it on eBay  
* Tactically acquire vending machine for grinding discs and other consumables
* Pub
* Pub
===Bike Area===
* Install Panel Lights

Latest revision as of 01:28, 29 January 2026

Metalworking

Electrical

  • Hang lights ✅ (complete except grinding room + one in far corner)
  • Install conduit ✅
  • Install trunking ✅
  • Pull cable ✅
  • Install temporary control box / switching solution ✅
  • Install control box feed (10A RCBO from main board, PVC conduit) ✅
  • Test & Inspection ✅
  • Remove last of temporary lighting solution ✅
  • 13A power circuit on near wall ✅
  • 13A power circuit on dance studio wall ✅
  • Welding interlock (WIP)
  • Heavy feed to interlock box (D63 - reuse from metalworking feed upstairs?)
  • Install welding sockets - will require them being removed from upstairs
  • Test & Inspection
  • Make and install unistrut post for bandsaw socket
  • 16/3 Socket for bandsaw (SWA on tray from DB down post to RCD in small box, RCD to socket)
  • Complete traywork install
  • Make and install rest of unistrut posts
  • Install back wall small power circuit
  • Install posts small power circuit (routing???)
  • Corridor power circuit (PVC conduit)
  • Install power for compressor (seperate feed, or tacked on to the end of the corridor power circuit)
  • Test & Inspection, issue EIC

Blocked Tasks

  • All of small grinding room
  • Hanging final light

Non-Electrical

  • Put the rest of the diffusers on the lights
  • Plug in the batteries on the emergency lights (technically electrical I suppose)
  • Move door currently on grinding room to far end of room
  • Establish what else needs to be done to the grinding room before it's sensible to install electrics in there (finish walls, boxing, etc)
  • Move stuff out of the way (particularly the pallet of metal things and the Warco - eek.)
  • Design and install curtains/other dividing solution between welding quarter and the rest of the room to ensure that grinding dust is mostly kept out of the rest of the area
  • Design and install ventilation setup for welding
  • Finish ceiling in far corner of main space to allow final light to be hung
  • Data cabling for NH-Tools
  • Move tools / benches etc into place!
  • Handles for doors
  • Investigate possible leak in grinding room?


Epilogue

  • Christen the room by smashing a bottle of Lucozade on it's bow (step one, find its bow...)
  • Remove all infra tools/supplies from Downstairs Members' Storage to Team Storage
  • Consider fire door (opening inwards probably not acceptable?)
  • Have Schneider DB disconnected and sell it on eBay
  • Tactically acquire vending machine for grinding discs and other consumables
  • Pub


Bike Area

  • Install Panel Lights