===Metalworking===
=Metalworking=


===Electrical===
==Electrical==


* Hang lights ✅ (complete except grinding room + one in far corner)
* Hang lights ✅ (complete except grinding room + one in far corner)
Line 27: Line 27:
* Test & Inspection, issue EIC
* Test & Inspection, issue EIC


====Blocked Tasks====
===Blocked Tasks===
* All of small grinding room
* All of small grinding room
* Hanging final light
* Hanging final light


===Non-Electrical===
==Non-Electrical==
* Put the rest of the diffusers on the lights
* Put the rest of the diffusers on the lights
* Plug in the batteries on the emergency lights (technically electrical I suppose)  
* Plug in the batteries on the emergency lights (technically electrical I suppose)  
Line 37: Line 37:
* Establish what else needs to be done to the grinding room before it's sensible to install electrics in there (finish walls, boxing, etc)
* Establish what else needs to be done to the grinding room before it's sensible to install electrics in there (finish walls, boxing, etc)
* Move stuff out of the way (particularly the pallet of metal things and the Warco - eek.)  
* Move stuff out of the way (particularly the pallet of metal things and the Warco - eek.)  
* Install curtains/other dividing solution between welding quarter and the rest of the room to ensure that grinding dust is mostly kept out of the rest of the area
* Design and install curtains/other dividing solution between welding quarter and the rest of the room to ensure that grinding dust is mostly kept out of the rest of the area
* Design and install ventilation setup for welding
* Design and install ventilation setup for welding
* Finish ceiling in far corner of main space to allow final light to be hung
* Finish ceiling in far corner of main space to allow final light to be hung
Line 43: Line 43:
* Move tools / benches etc into place!
* Move tools / benches etc into place!
* Handles for doors  
* Handles for doors  
* Investigate possible leak in grinding room?


====Epilogue====
 
==Epilogue==
* Christen the room by smashing a bottle of Lucozade on it's bow (step one, find its bow...)  
* Christen the room by smashing a bottle of Lucozade on it's bow (step one, find its bow...)  
* Remove all infra tools/supplies from Downstairs Members' Storage to Team Storage
* Remove all infra tools/supplies from Downstairs Members' Storage to Team Storage
* Consider fire door (opening inwards probably not acceptable?)  
* Consider fire door (opening inwards probably not acceptable?)  
* Have Schneider DB disconnected and sell it on eBay  
* Have Schneider DB disconnected and sell it on eBay  
* Tactically acquire vending machine for grinding discs and other consumables
* Pub
* Pub
===Bike Area===
* Install Panel Lights

Latest revision as of 01:28, 29 January 2026

Metalworking

Electrical

  • Hang lights ✅ (complete except grinding room + one in far corner)
  • Install conduit ✅
  • Install trunking ✅
  • Pull cable ✅
  • Install temporary control box / switching solution ✅
  • Install control box feed (10A RCBO from main board, PVC conduit) ✅
  • Test & Inspection ✅
  • Remove last of temporary lighting solution ✅
  • 13A power circuit on near wall ✅
  • 13A power circuit on dance studio wall ✅
  • Welding interlock (WIP)
  • Heavy feed to interlock box (D63 - reuse from metalworking feed upstairs?)
  • Install welding sockets - will require them being removed from upstairs
  • Test & Inspection
  • Make and install unistrut post for bandsaw socket
  • 16/3 Socket for bandsaw (SWA on tray from DB down post to RCD in small box, RCD to socket)
  • Complete traywork install
  • Make and install rest of unistrut posts
  • Install back wall small power circuit
  • Install posts small power circuit (routing???)
  • Corridor power circuit (PVC conduit)
  • Install power for compressor (seperate feed, or tacked on to the end of the corridor power circuit)
  • Test & Inspection, issue EIC

Blocked Tasks

  • All of small grinding room
  • Hanging final light

Non-Electrical

  • Put the rest of the diffusers on the lights
  • Plug in the batteries on the emergency lights (technically electrical I suppose)
  • Move door currently on grinding room to far end of room
  • Establish what else needs to be done to the grinding room before it's sensible to install electrics in there (finish walls, boxing, etc)
  • Move stuff out of the way (particularly the pallet of metal things and the Warco - eek.)
  • Design and install curtains/other dividing solution between welding quarter and the rest of the room to ensure that grinding dust is mostly kept out of the rest of the area
  • Design and install ventilation setup for welding
  • Finish ceiling in far corner of main space to allow final light to be hung
  • Data cabling for NH-Tools
  • Move tools / benches etc into place!
  • Handles for doors
  • Investigate possible leak in grinding room?


Epilogue

  • Christen the room by smashing a bottle of Lucozade on it's bow (step one, find its bow...)
  • Remove all infra tools/supplies from Downstairs Members' Storage to Team Storage
  • Consider fire door (opening inwards probably not acceptable?)
  • Have Schneider DB disconnected and sell it on eBay
  • Tactically acquire vending machine for grinding discs and other consumables
  • Pub


Bike Area

  • Install Panel Lights