Hackspace 2.5/ToDo
Jump to navigation
Jump to search
Metalworking
Phase Zero: Lighting
Electrical:
- Hang lights (done, except grinding room + one in far corner)
- Install conduit (done)
- Install trunking (WIP)
- Pull cable
- Install temporary control box / switching solution
- Install control box feed (10A RCBO from main board, PVC conduit)
- Test & Inspection, issue EIC
- Remove last of temporary lighting solution
Non-electrical:
- Finish ceiling in far corner to allow final light to be hung
Phase One: Welding & Grinding
Electrical:
- Welding interlock (WIP)
- Heavy feed to interlock box (D63 - reuse from metalworking feed upstairs?)
- Install welding sockets - will require them being removed from upstairs (trunking/SWA)
- 16/3 supply to grinding room, but see below
- Install small power circuit to bay (galv conduit)
- Test & Inspection, issue EIC
Non-electrical:
- Move door from grinding room to far end of room
- Establish what else needs to be done to the grinding room before it's sensible to install electrics in there (finish walls, boxing, etc)
- Move stuff out of the way (particularly the pallet of metal things and the Warco - eek.)
- Install curtains/other dividing to ensure that grinding dust is kept out of the rest of the area
- Consider the ventilation situation
Phase Two: The rest
Electrical:
- Complete the traywork
- Heavy feeds (3x 16/3)
- Small power circuits (galv conduit)
- Corridor power circuit (PVC conduit)
- Install power for compressor (seperate feed or tacked on to the end of the corridor power circuit)
Non-electrical:
- Install unistrut posts on the pillars ala Dusty Area
- Remove random leftover wood, insulation, etc
- Data cabling for NH-Tools
- Move tools / benches etc into place!
Epilogue
- Christen the room by smashing a bottle of Lucozade on it's bow (step one, find its bow...)
- Remove all infra tools/supplies from Downstairs Members' Storage to Team Storage
- Consider fire door (opening inwards probably not acceptable?)
- Have Schneider DB disconnected and sell it on eBay